People Inc. Project Update – August

People, Inc., is currently reporting work on the following items for the construction project located at 135 Evans (formerly Blocher Homes) in the Village of Williamsville. This list reflects project milestones to be completed in the month of August.

  • Finish foundation at North Building
  • Finish domestic water and sewer lines on site
  • Finish window installation at Existing Building
  • Start framing at North Building
  • Start prime & paint at Existing building
  • Continue brick & siding work at South Building
  • Continue roof work at South, Middle, and North Buildings
  • Continue to rough in MEPs in Existing and Middle Buildings
  • Continue framing and drywall work at Existing and South Buildings